Continuous Commissioning® Services
SEA has helped reduce utility costs by 27% for a total cost savings of $114,793 over 14 months.
AT A GLANCE
Calhoun Community College Facts
34M Construction / Renovation Cost
$114,793 Total Cost Savings
90k Square Feet
2016 Completion Date
About the Facility
Calhoun Community College Huntsville / Cummings Research Park campus is the only two year college campus in the nation located in a major research park. This $34M construction / renovation project was recently completed providing increased access and a more collegiate environment for students. Sain Engineering Associates (SEA) was contracted to develop the energy strategy and supplement that strategy with a master plan to provide a long-term vision for making sound energy decisions to reduce energy consumption, minimize operating expenditures and extend equipment life.
SEA developed the energy strategy by conducting site surveys, interviewing staff and coordinating the master plan by analyzing the age and condition of existing equipment. SEA also provided assistance in making recommendations for energy program staffing and financing plans.
Recommended Solutions
The documented utility savings resulted from optimizing HVAC equipment accordingly:
Optimized hot water supply temperature to reduce boiler demand while maintaining heating needs
Corrected air handling units operating inefficiently
Monitored zone reheat valves for overcooled areas, verified flow rates and design
Modified terimnal box flow rates to reduce unoccupied cooling/heating
Investigated leaking or open heating values on air handling units/terminal boxes
Examined chilled water valves for leakage
Programmed roof top units to reset the supply air temperature
Adjusted building pressure setpoint on roof top units to prevent excessive exhaust fan operation
Adjusted economizer setpoints on roof top units to better utilize cool, low humidity oustide air
Tested outside air and return air damper operation on air handling units
Built dashboard to easily monitor air handling unit operation, terminal box reheats, chilled and hot water temperatures